| 1 | 7.4968 | 4.5172 | Osun | 8030 | Sterling & Wilson Nig Ltd. | Captive 8.03MW Gas Based Power Plant at Obafemi Awolowo University, Ile-Ife, Osun State | 8400 | 8450350746.48 | 65 | Gas Engine Turbines and accessories delivered to the project site. Which includes Fresh Air Fans; Top container; Low Tension Piping; Inlet Air System; Air Conditioner; Exhaust Silencer, etc.
|
| 2 | 6.5158 | 3.3898 | Lagos | 8030 | Sterling & Wilson Nig Ltd. | Captive 8.03MW Gas Based Power Plant at University of Lagos | 8400 | 6850052048.11 | 41 | Site sand filling and fencing have been completed. 8Km of Streetlight successfully installed. - First batch of the Work/ Training Center materials have been delivered to site |
| 3 | 6.2459 | 7.1199 | Anambra | 2496 | METKA West Africa Ltd. | Captive 2.0MW Solar Hybrid Power Plant at Nnamdi Azikiwe University Awka | 4380 | 3584934274.97 | 98 | 2..00MW PV Panels successfully installed, All major equipment have been installed including, PV panels, Transformers, Inverters, Batteries, Back DG sets, etc. 9.48km of streetlights have been installed. Workshop/ Training Center is 98% completed. |
| 4 | 13.1246 | 5.1994 | Sokoto | 2000 | METKA West Africa Ltd. | Captive 2.0MW Solar Hybrid Power Plant at Usman Danfodio University Sokoto | 4390 | 3667467604 | 92 | 8.65km length of streetlights have been installed. 2..00MW PV Panels successfully installed All major equipment have been installed including, PV panels, Transformers, Inverters, Batteries, Back DG sets, etc. |
| 5 | 6.1318 | 8.1413 | Ebonyi | 1155 | Sterling & Wilson Nig Ltd. | Captive 1.0MW Solar Hybrid Power Plant at Alex Ekwueme University Ndufu-Alike Ikwo | 2800 | 2177698591.32 | 100 | The Project was successfully commissioned on 2nd August 2019 with +9,500 staff and students now receiving adequate and reliable power. The project is in the process of being handed over to the university management, having completed over 1 year of O&M services and successfully trained the university staff to operate and maintain the power plant, WTC and streetlights.
|
| 6 | 5.5693 | 5.765 | Delta | 624 | METKA West Africa Ltd. | Captive 0.5MW Solar Hybrid Power Plant at University of Petroleum Resources Effurun | 1350 | 1621596356.04 | 100 | All components of the project have been completed, including the pre commissioning tests on the distribution network. It is ready to be officially commissioned and to commence the O&M phase of the project.
|
| 7 | 10.2784 | 9.7969 | Bauchi | 554 | Sterling & Wilson Nig Ltd. | Captive 0.5MW Solar Hybrid Power Plant at Abubakar Tafawa Balewa University, Bauchi | 1120 | 1464381750.32 | 100 | The Project was technically commissioned on 2nd February 2020 and the university has been receiving adequate and reliable power since then. The project is set for official commissioning and handover having completed the O&M phase and trained the university staff, in January 2021
|
| 8 | 11.9708 | 8.4347 | Kano | 3503 | METKA West Africa Ltd. | Captive 3.0MW Solar Hybrid Power Plant at Bayero University, Kano State | 7100 | 5095810001.63 | 100 | The Project was successfully commissioned on 3rd September 2019 with +58,000 staff and students receiving adequate and reliable power. After completion of over 1 year of operations and maintenance of the power plant and training of the university staff to operate and maintain same, provided by the EPC/O&M Contractor, the EEP project was handed over to the university management on the 3rd December 2020 with all relevant project documentation .
|
| 9 | 7.7322 | 8.5391 | Benue | 4006 | Sterling & Wilson Nig Ltd. | Captive 3.5MW Solar Hybrid Power Plant at University of Agriculture Makurdi | 8250 | 6052856508.32 | 100 | 3.50MW PV Panels (8.25 total installed capacity) successfully installed. This project commenced O&M in July 2020, though was officially commissioned on the 4th December 2020
|